ICL Teesdock - Silo Repairs

  • david foster
  • Oct 11, 2021
  • 1 min read

Updated: Dec 7, 2022

Good progress in being made on the repairs to the south silo which stores over 60,000 tons of material. The concrete plinths (no50) and steel structure which support the building are in the process of getting refurbished. Documents and method statements provided by Ian Farmer Associates, actual graft supplied by Concrete Repairs Ltd.

Completed on time with no variations. Many thanks to all the Project Team.








 
 
 